1911 Gold Provides Update on Strategic Plans for True North Mine

In This Article:

TORONTO, June 20, 2024 /CNW/ - 1911 Gold Corporation ("1911 Gold" or the "Company") (TSXV: AUMB) (OTC: AUMBF) is pleased to provide an update on the strategic plans for the advancement of the True North Mine, including 43-101 mineral resource estimate update, located within the prolific Rice Lake property in southeastern Manitoba, Canada.

1911 Gold (CNW Group/1911 Gold Corporation)
1911 Gold (CNW Group/1911 Gold Corporation)

Project Update

  • Resource Model Quality: Completed a detailed review of the current Mineral Resource geological model and confirmed the integrity of the geological interpretation.

  • Drill Hole Data Review: Completed a review of the True North drill hole data, identifying areas where information is required but confirming its integrity and accuracy.

  • Mineral Resource Estimate: Completed validation of the current Mineral Resource Estimate with results being able to re-produce the tonnes, grades and contained ounces.

  • Near Mine Geology and Structural Controls: Confirmed the presence of major regional structures hosted by mafic lithological units, the primary control for gold mineralization at True North, critical for target generation in the future.

  • Manitoba Mineral Development Fund ("MMDF") Grant: The Company was approved for $180,986 in funding under Manitoba's resource development program administered by the MMDF.

Forward Plans

  • Resource Model Update and Database Review: Complete the updating of all geological wireframes as well as review and validate the project database by the end of June to support the updated Mineral Resource Estimate.

  • Mineral Resource Estimate Update: Lions Gate Geological Consulting engaged to complete the Mineral Resource Update planned for completion by early August 2024.

  • True North Mineral Resource Extensions: Identify significant target areas for potential extension of the mineral resource inventory for follow up exploration.

  • New True North Drill Targets: Generate additional targets for gold mineralization adjacent to the True North Mine area within favourable geological settings.

  • Regional Drill Target Review: Following completion of the updated Mineral Resource Estimate, the Company will also focus on defining priority, drill-ready targets within the Company's 63,036-hectare Rice Lake Greenstone Belt.

  • Resource Growth: Focus on exploration for significant resource growth through the remainder of 2024.

  • Economic Analysis: Commence work on a preliminary mine plan and re-start analysis upon completion of the new Mineral Resource Estimate.

Mr. Shaun Heinrichs, President and CEO of 1911 Gold, commented, "Our team's diligent efforts in assessing and updating the geological model have significantly advanced our understanding of the True North mine. Using this updated, robust geological interpretation we are actively working on prioritizing targets that have resource expansion potential within the existing mine footprint for follow up after completing the Mineral Resource Estimate. We are also grateful for the ongoing support we have received from the Manitoba government and look forward to achieving further milestones in building a core resource project for the province."