Endeavour Silver Reports Q3 2024 Production Results

Endeavour Silver Corporation
Endeavour Silver Corporation

In This Article:

VANCOUVER, British Columbia, Oct. 08, 2024 (GLOBE NEWSWIRE) -- Endeavour Silver Corp. (“Endeavour” or the “Company”) (NYSE: EXK; TSX: EDR) is pleased to report third quarter 2024 production of 874,717 silver ounces and 9,290 gold ounces, for silver equivalent1 (“AgEq”) production of 1.6 million ounces. Total year-to-date production of 6.0 million AgEq ounces is tracking towards the updated 2024 production guidance of 7.3 million to 7.6 million AgEq ounces. All amounts are in U.S. dollars unless stated otherwise.

"The trunnion failure at the Guanaceví mine poses a significant short-term challenge for the Company; however, it's how we manage these difficult moments that often shapes our long-term success.” said Dan Dickson, Chief Executive Officer. "The ingenuity, commitment, and hard work of our team have been crucial in reducing the impact on the mine and the surrounding community. We remain focused on further mitigating the effects and look forward to returning Guanaceví to full production capacity in December.”

Q3 2024 Overview

  • Guanaceví Production Impacted by the Trunnion Failure: Production decreased in August and September due to a trunnion failure of the primary ball mill (see news release from August 12, 2024). Production for Q3 2024 amounted to 768,905 silver ounces and 2,828 gold ounces. Estimated fabrication timing remains at 15 weeks with the mine being back to full operations in December 2024.

  • Bola?itos Results Remain Consistent: With throughput remaining steady, gold production continues to be slightly above plan due to higher gold grades. Silver production continues to be slightly below plan due to lower silver grades. Processed ore grades are expected to have similar variation for the fourth quarter.

  • Metal Sales and Inventories: Sold 1,017,392 silver ounces and 9,412 gold ounces during the third quarter. A total of 109,719 silver ounces and 401 gold ounces of bullion inventory and 8,202 silver ounces and 560 gold ounces in concentrate inventory were held at quarter end.

  • Terronera Senior Secured Debt Facility: Drawdowns totaling $25 million were made during Q3 2024 to develop the Terronera mine, and a further and final drawdown of $35 million subsequent to quarter end (see news release dated April 10, 2024).

Q3 2024 Mine Operations

In August, the Company reported a primary ball mill trunnion failure at the Guanaceví mine. Temporary modifications were completed within the plant to re-purpose one of the regrind mills as the primary ball mill. The temporary modifications allowed throughput to average 565 tonnes per day since re-start after the trunnion failure. The plant team is closely monitoring the operation of the regrind mills to ensure continued reliability and high mechanical availability, including increased planned maintenance down days during this temporary period.