Ur-Energy Provides 2024 Q2 Update: Lost Creek and Shirley Basin

ACCESSWIRE · Ur-Energy Inc.

In This Article:

LITTLETON, CO / ACCESSWIRE / July 16, 2024 / Ur-Energy Inc. (NYSE American:URG)(TSX:URE) (the "Company" or "Ur-Energy") provides the following 2024 Q2 updates on Lost Creek production operations and guidance, Shirley Basin construction, and our uranium sales contract book.

John Cash, the Company's CEO and Chairman of the Board, stated, "We are pleased that continuing advances at Lost Creek resulted in increased production quarter-over-quarter. The Lost Creek drilling and construction teams have further refined their work plans to facilitate our schedule of bringing a new header house online each month. This progress enables the continuing increase in production flow which will allow us to achieve our production targets. Importantly, the production patterns continue to be receptive to our mining methods, exhibiting strong production grades.

"We are happy to see the level of construction activity on the ground at Shirley Basin as well as the progress on procurement, and detailed engineering and planning to facilitate our planned buildout. We look forward to bringing uranium in situ recovery back to its birthplace at Shirley Basin and solidifying Ur-Energy's position as the dominant producer in the Great Divide Basin and Shirley Basin Districts of Wyoming."

Lost Creek Production Operations

Lost Creek production is advancing with three header houses having come online in 2024 H1. During Q2 we captured approximately 70,679 pounds, dried and packaged 64,170 pounds and shipped 70,390 pounds U3O8. We are pleased with the notable increase in each of these production numbers compared with Q1 production. Notwithstanding these improvements, we are guiding to the lower side of our earlier 2024 production guidance of 550,000 to 650,000 pounds captured on IX resin.

At quarter end, our in-process inventory was approximately 86,204 pounds, our drummed inventory at Lost Creek was 21,570 pounds, and our finished inventory at the conversion facility was 74,625 pounds U3O8. Our next shipment to the conversion facility is scheduled for late July.

Header House (HH) 2-9 came online this week and HH2-10 is scheduled to come online mid-August. Our construction crew is now on track to meet its goal of routinely completing a new header house approximately every thirty days. Throughout Q2 we had 12 drill rigs working at Lost Creek; we anticipate additional drill rigs mobilizing to Lost Creek in coming weeks.

Fabrication of HH2-10 is complete and fabrication of HHs 2-11 through 2-13 is in progress in our Casper construction shop. We recently took delivery of and deployed two downhole geophysical logging trucks that were ordered in early 2023.