Sierra Madre Receives Regulatory Approval for Dry Stack Tailings Deposition on Existing Tailings Impoundment, Paste Backfill of Tailings in Underground Workings and Surface Drilling Pad Sites

In This Article:

Vancouver, British Columbia--(Newsfile Corp. - May 28, 2024) - Sierra Madre Gold and Silver Ltd. (TSXV: SM) (OTCQX: SMDRF) ("Sierra Madre" or the "Company") is pleased to announce that SEMARNAT, the federal Mexican regulatory agency in charge of environmental permitting, has approved modifications to the existing operating permit for the Guitarra Mine and Mill complex, located in the State of Mexico, Mexico. These modifications will allow for:

  • Dry Stack Tailings Deposition at the Active Tailings Facility Site, TSF 1-3

  • Construction of a Tailings Filter Plant Adjacent to the Existing Mill

  • Paste Backfill Using Tailings in the Guitarra Underground Mine

  • 58 surface drilling pad locations

Dry Stack Tailings Approval and Next Steps

Regulatory approval for dry stack tailings deposition is a significant milestone for Sierra Madre as it moves forward with the possible mine restart at Guitarra. This approval allows the Company to transition from conventional tailings deposition to a more modern system and delays the near-term capital expense of building the fully permitted 5.8 million tonne TSF 4. The use of dry stack deposition will result in more process water being recycled and will allow more tonnes of tailings to be deposited within the existing footprint of TSF 1-3. Dry stacked tailings are the more environmentally responsible alternative and provide a higher level of safety and security long term.

TSF 1-3 has two conventional tailings deposition sites with a remaining capacity of 230,000 tonnes which the company plans to use in initial startup operations. Construction on one site began in April and is scheduled for completion before the onset of the rainy season in June. The dam, or bordo, is being built in 30 cm compacted lifts. The inner bordo face and bottom will be covered with a high-strength HDPE liner, as per accepted industry practices. At the processing plant's operating capacity of 500 tonnes per day, the two expansions will be sufficient for a minimum 15 months of operations, providing the Company with time to complete the design and construction of a combined dry stack and paste backfill tailings disposal system.

High-level studies conducted by Stantec Consulting International LLC and Ingenieria y Construcción de Presas S.A. de C.V. suggest that TSF 1-3 may potentially have a dry stack tailings capacity of at least 500,000 tonnes. The Company has decided to conduct additional geotechnical drilling and studies during the upcoming rainy season to obtain additional high-water saturation data before proceeding with the final layout and design work. This will enable the Company to make better-informed operational decisions.